A 3,140-ton span is placed on pillars of the Padma Bridge by a China-made crane vessel in Bangladesh Feb. 20, 2019. China Major Bridge Engineering Company on Wednesday successfully installed the 7th span of Bangladesh's largest Padma Bridge, making over 1 km of the bridge visible so far. (Xinhua/Duan Yonghong)
DHAKA, Feb. 20 (Xinhua) -- China Major Bridge Engineering Company on Wednesday successfully installed the 7th span of Bangladesh's largest Padma Bridge, making over 1 km of the bridge visible so far.
The 3,140-ton span was placed on the pillars 35 and 36 of the bridge on Wednesday afternoon.
With the installation of the 150-meter long span, the 7th span among the 41 spans has been installed on the 6.15-km bridge and about 1,050 m of the bridge is now visible.
In December 2015, Bangladeshi Prime Minister Sheikh Hasina inaugurated the main works of Padma Bridge project, the biggest of its kind for the country, by unveiling its foundation plaque.
In June 2014, the Bangladeshi government awarded China Major Bridge Engineering Company Limited a 1.55-billion-U.S.-dollar contract to build core structure of the Padma Bridge project.
Apart from connecting nearly 30 million people in Bangladesh's southwest region to the rest of the country, the bridge will enhance regional trade and collaboration along the Asian highway No. 1 and the Trans-Asian railway network.